This contract is for drainage improvements in the Kingslake Forest Subdivision for Harris County Precinct 1. The project includes stormsewer improvements, removal and replacement of existing stormsewers, and the addition of a detention basin. The contract was awarded to E.P. Brady, LTD. for $6,447,711. The key aspects of this contract include:
* Drainage improvements in the Kingslake Forest Subdivision
* Stormsewer improvements along multiple streets
* Removal and replacement of existing stormsewers
* Addition of a detention basin
* Mitigation for the impacts to Greens Bayou tributary P127-00-00
* Recreational features such as mature trees, signage, trash receptacles, and benches
* Reduction of flood risk and strengthening of resiliency in Harris County