The City of Independence, Missouri Power & Light Department is soliciting for a supplier to design, furnish, fabricate, assemble, manufacture, test, and deliver to the job site a protective relay panel and other equipment as specified. The scope of work includes providing relay control panels, loose items, and other equipment, as well as performing factory assembly and tests. The project milestones indicate a bid period from September 30, 2025 to November 5, 2025, with a scheduled delivery to the project site on June 1st, 2026. Key aspects of the contract include:
• Providing relay control panels and loose items
• Performing factory assembly and tests
• Delivering equipment to the project site
• Providing technical assistance for inspection, installation, adjustment, testing, and initial energization
• Correcting all wiring and manufacturing errors discovered in the field promptly and at no cost to the Owner