Awarded vendors
- Cross Construction Services, Inc.
Description
This contract is for the demolition of water treatment plant facilities at Lake Hayes and Heathrow. The contract was awarded to Cross Construction Services, Inc. and is valued at an estimated $180,000. The contract duration is approximately 180 days, starting from November 4, 2024, and ending on May 2, 2025. The scope of work includes the demolition of the facilities, and the contractor is responsible for ensuring that all work is completed in accordance with the contract specifications and regulations.
• The contract includes provisions for payment, performance, and termination.
• The contractor is required to maintain certain insurance policies and to comply with all applicable laws and regulations.
• The contract also includes a dispute resolution process in the event of any disagreements between the parties.