The City of Napa, Utilities Department, has awarded a contract for the Redwood Road Water Main CIPP Rehab Project to Insituform Technologies, LLC. The project involves the rehabilitation of the water main using cured-in-place pipe (CIPP) technology. The contract was awarded on February 8, 2024, with a total bid price of $597,643. The project includes various items such as mobilization, control of work, pothole existing utilities, erosion and sediment control plan, traffic control, shoring, insertion and receiving pits, annular grout at ex. casing, CCTV - pre, pipe cleaning, and other related work.
• The project is located in Napa, California.
• The contract was awarded through an Invitation for Bid (IFB) process.
• The estimated construction cost for the project is $185,000.
• The contract includes a bid bond response information form, provisions and technical specs, addendums, and other related documents.