The Grove Street Drainage Improvement Project involves the construction of drainage facilities, including concrete headwalls, trash racks, and concrete armored overflow crossings. The project is located on Grove Street from Lincoln Blvd. to Virginia Ave. in Butte County, California. The engineer's estimate for the project is $59,000. The contract was awarded to three vendors: Santos Excavating, Inc., Franklin Construction, Inc., and R&R Horn, Inc. The project consists of various tasks, including clearing and grubbing, ditch excavation, and the installation of reinforced concrete pipes.
• The project requires the construction of concrete headwalls and trash racks.
• The project involves the installation of reinforced concrete pipes and concrete armored overflow crossings.
• The project requires the clearing and grubbing of the area, as well as ditch excavation.
• The project involves the installation of aggregate base and concreted rock slope protection.
• The project requires the removal and relocation of roadside signs.