The contract is for the reconstruction of Baldwin Street in Rapid City, South Dakota. The project involves reconstructing sanitary sewer, water, and street. The bid results show that the contract was awarded to Rapid Const. with a base bid of $4,863,000.00. The engineer's estimate for the project was $4,370,000.00. The contract also includes addenda and notes. The scope of work includes reconstruction of the street, sanitary sewer, and water. The project is located in Rapid City, South Dakota, and the bid was submitted on January 26, 2016.
• The project involves reconstruction of sanitary sewer, water, and street.
• The contract was awarded to Rapid Const.
• The base bid was $4,863,000.00.
• The engineer's estimate was $4,370,000.00.
• The contract includes addenda and notes.
• The project is located in Rapid City, South Dakota.