This contract involves the demolition and secure abatement of a garage located at 709 Mandrell Street in Mobile, Alabama, along with extensive site remediation. The contractor must perform wet demolition, utility disconnection, hazardous material handling (lead‑based paint/asbestos), debris removal, erosion and sediment control, seeding, and a series of post‑demolition repairs and finishes as outlined in Addendum 1. The work must be completed within 15 calendar days of receiving a notice to proceed, with liquidated damages of $250 per day for delays beyond that period. The City of Mobile Municipal Enforcement Department issued the RFQ, and the award was given to DEESE LAWN CARE.
• Wet demolition of the garage and full securing of the remaining structure.
• Utility caps, hazardous‑material disposal, erosion‑control BMPs, and site seeding.
• Additional scope from Addendum 1: pressure‑wash, painting, polycarbonate window inserts, door security, minor roof and trim repairs, and final lot cleanup.
• Performance period of 15 days with $250/day liquidated‑damage clause.
• Single‑vendor award; no set‑aside or renewal provisions identified.