The contract is for the construction of a sidewalk at East Meyer Avenue for Harris County Precinct 2. The project involves the construction of approximately 3,750 linear feet of 5-foot wide sidewalks, including removing old concrete, installing new concrete, and providing other improvements to the pedestrian realm. The contract was awarded to Environmental Allies, Inc. for a total amount of $664,484. The project is expected to be completed within a year, and the contract may be renewed after the end date. Key aspects of the project include:
• Construction of sidewalks and curbs
• Installation of reinforced concrete pipe
• Removal and relocation of existing structures
• Installation of traffic signs and markings
• Provision of SWPPP maintenance
The project aims to improve the pedestrian realm and community connectivity in the area.