The Big Horn Offsite Well No 4 (W-129) Rehabilitation Project involves the rehabilitation of the pump at the Big Horn Offsite Well Number 4, including removing the pump, inspecting all parts, well video, cleaning of the well, replacement of the pump and all appurtenances, and installing two well sounding tubes. The contract was awarded to Nor-Cal Pump and Well Drilling, Inc. in the amount of $53,868.00. The project is located at 9751 Big Horn Boulevard, Elk Grove, CA 95757.
• The project requires a General Engineering Contractor, Class A, C-57, or C-61 license.
• The engineer's estimate for the project is $110,000.
• The contract was awarded through a competitive bidding process, with three bidders submitting proposals.
• The project is subject to the requirements of the current public health order, and bidders were required to adhere to these requirements during the pre-bid meeting and walk-through.