The contract is for the rehabilitation of the Wilburton Pump Station. The scope of work includes demolition of existing pumps, valves, piping, and other equipment, as well as the installation and testing of new pumps, piping, and electrical equipment. The contract also includes work on the pump station's structural and mechanical systems. The bid tabulation sheet lists the bids from five different vendors, with Award Construction submitting the highest bid at $1,712,605.50.
• The contract is for the rehabilitation of the Wilburton Pump Station
• The scope of work includes demolition and installation of new equipment
• The contract includes work on the pump station's structural and mechanical systems
• Five vendors submitted bids, with Award Construction submitting the highest bid
• The bid tabulation sheet provides a detailed breakdown of the bids from each vendor