The Four Rivers Sanitation Authority is procuring a single‑prime lump‑sum contract to rehabilitate the roof of the Old Main Pump building at its Rockford wastewater treatment plant. The scope includes selective demolition of existing clay tiles, repair of the gypsum deck, installation of a new ice‑and‑water shield, re‑installation of salvaged tiles, and a new copper snow‑guard system, plus all required temporary facilities, safety controls, and close‑out documentation. The contract is awarded to Roofing Systems, Inc. and requires a 10 % bid bond, a 100 % performance bond, and compliance with extensive insurance, prevailing‑wage, and environmental statutes. The work must be completed within 35 working days from the notice to proceed, with liquidated damages of $300 per calendar day for missed deadlines.
• Demolition, deck repair, and roof‑system installation (clay tiles, ice‑and‑water shield, snow‑guard).
• Mandatory bonding (10 % bid bond, 100 % performance bond) and insurance (general liability $1M, auto $1M, workers’ comp $500K, umbrella $2M).
• Strict compliance with Illinois prevailing‑wage, steel‑product, employment, OSHA, and clean‑construction regulations.