The City of Houston – Houston Airport System awarded a contract to Posillico Civil, Inc. for the regrooving and re‑texturing (grind and groove) of Runway 9‑27 at George Bush Intercontinental Airport (IAH). The work includes pavement removal, concrete spall repair, diamond and asphalt grinding, groove cutting, joint sealing, surface preparation, runway and taxiway markings, asphalt seal‑coating, and associated electrical work such as removal and installation of in‑pavement lighting fixtures. The contract is valued at approximately $7.02 million, with a 15 % DBE participation goal, and must be completed within 60 calendar days from the date of commencement.
• Primary scope: runway surface grind, groove, and mark‑up.
• Includes extensive pavement preparation, joint sealing, and lighting fixture replacement.
• Requires compliance with FAA, DBE, Pay‑or‑Play, prevailing‑wage, and Buy‑American requirements.