Awarded vendors
- GB Hawk Const., LLC
Description
This contract is for lead abatement work at 80 Vesper St. in Akron, Ohio. The work includes exterior and interior lead abatement, as well as healthy homes repairs such as fixing plumbing leaks and repairing water-damaged flooring. The contract was awarded to GB Hawk Const., LLC for a total of $8,500. The contractor is required to follow all applicable local building codes and regulations, including OSHA and EPA guidelines. The contractor must also provide a warranty for all work completed. Some key points from the contract include:
* The contractor must attend a mandatory pre-bid meeting to submit a bid.
* The contractor must have a current registration, bond, and insurance on file with the appropriate jurisdiction's building department.
* The contractor must carry a minimum of $2,000,000 of general commercial liability insurance and $1,000,000 of commercial auto liability.
* The contractor must list the county of Summit as an additional insured on their insurance policy.
* The contractor must follow all HUD requirements and EPA RRP guidelines for lead abatement work.
* The contractor must provide a clearance test at no cost to the owner, and any additional clearances must be paid for by the contractor.
* The contractor must complete all work within 30 days of signing the contract.
* The contractor must respond to all phone calls and emails within 24 hours.
Some of the specific work items included in the contract are:
* Garage door casing-side A-paint stabilization in accordance with HUD regulations
* Garage man door-side B-remove existing door and board seal opening with treated plywood
* Side B entry door and casing-remove existing door and replace with steel pre-primed pre-hung door with weather stripping and a dead bolt
* Repair plumbing in basement-it is leaking from incorrect installation of newly installed first floor bathroom
* Repair water damaged flooring in first floor bathroom around shower unit
* Repair water damaged flooring in second floor bathroom around the toilet
* Adress ceiling leak in second floor bathroom and repair ceiling damage
The contract also includes several terms and conditions, such as:
* The contractor must upload EPA 8 hour lead safe certificates with their bid, along with their firm registration with the EPA.
* The contractor must carry workers' compensation insurance and provide proof of coverage.
* The contractor must comply with all federal, state, and local laws and regulations.
* The contractor must indemnify and hold harmless the owner and their agents and employees from any claims or damages arising from the work.
* The contractor must maintain accurate and detailed records of all work performed, including before and after photos.