This contract is for lead abatement work at 48 Mull Ave. in Akron, Ohio. The work includes removal and replacement of windows, doors, and other components, as well as installation of smoke detectors and CO detectors. The contract also requires the contractor to follow HUD regulations and guidelines for lead-based paint hazard control. The total value of the contract is estimated to be around $20,000. The scope of work includes:
* Removal and replacement of basement cabinet doors and frames
* Painting and stabilizing of basement support columns
* Removal and replacement of basement stairway stringers, risers, and treads
* Installation of steel pre-primed pre-hung doors with weather stripping and dead bolts
* Installation of smoke detectors and CO detectors
* Removal and replacement of windows
* Installation of vinyl siding and wrapping of exterior components with house wrap.
The contract has a duration of 30 days and requires the contractor to complete the work within this timeframe.