The Town of Fountain Hills awarded a contract to Kimley-Horn and Associates, Inc. for a Traffic Signal Design Study. The contract has a duration of 3 years, with an initial term length of 1 year and two renewal options. The contract value is estimated to be $154,597. The scope of work includes engineering design services. Key points-of-contact include Rob Durham, Procurement Administrator, and Justin Weldy, Public Works Director.
• The contract was signed on December 7, 2021, and has been renewed once, with the current end date being June 30, 2024.
• The contract has a budget of $154,597.
• The vendor, Kimley-Horn and Associates, Inc., is responsible for providing engineering design services.
• The contract has been signed by representatives of both the Town of Fountain Hills and Kimley-Horn and Associates, Inc.