This contract concerns the complete demolition of a condemned building located at 1321 Gary Street, covering Lots 8 & 9. The City of Fort Smith’s Engineering Department will oversee the work, which includes removing all structural components, site clearing, and proper disposal of debris. The procurement was conducted through an open competition, with bids received on 15 Nov 2023 and the lowest bid ($5,300) submitted by NEWHART CONSTRUCTION recommended for award.
• Project scope: full demolition and site preparation of a condemned municipal structure.
• Procurement method: full and open competition with six vendors submitting bids.
• Recommended awardee: NEWHART CONSTRUCTION (lowest bid).