The Hillcrest Drainage Improvement Project involves the construction and replacement of storm drainage pipes, outfall structures, inlets, and manholes, as well as the reconstruction of pedestrian curb ramps and replacement of curb and gutter segments. The project also requires coordination with P.G. & E. for a gas main relocation. The engineer's estimate for the project is $3.0 million, and the apparent low bidder is McGuire and Hester with a total bid of $3,913,891.00. The project is being managed by the City of Roseville's Public Works department.
• The project includes construction and replacement of storm drainage pipes and related structures
• The project requires reconstruction of pedestrian curb ramps and replacement of curb and gutter segments
• The project involves coordination with P.G. & E. for a gas main relocation
• The engineer's estimate for the project is $3.0 million
• The apparent low bidder is McGuire and Hester with a total bid of $3,913,891.00