The City of Independence, Missouri is soliciting bids from qualified firms to replace fourteen single pole structures, thirteen are transmission poles and one is a guy pole. The contractor must coordinate transfer of all communications cables from old to new structures in a timely manner. The estimated labor cost is $325,500.00. The contract was awarded to Black & McDonald for a total cost of $291,016.67.
• The contract involves replacing fourteen single pole structures
• The contractor must coordinate transfer of all communications cables from old to new structures
• The estimated labor cost is $325,500.00
• The contract was awarded to Black & McDonald for a total cost of $291,016.67