The contract is for the replacement of windows at the Fairgrounds Pavilion in Moffat County, Colorado. The scope of work includes removing existing windows, installing new vinyl replacement windows, and completing any necessary framing, installation, and trimming. The contract was awarded to JMAR Construction for a total amount of $10,425.00. The key points of the contract include the removal of existing windows, installation of new windows, and completion of any necessary work to give an air-tight seal.
• The contract is for the replacement of windows at the Fairgrounds Pavilion.
• The scope of work includes removing existing windows and installing new vinyl replacement windows.
• The contract was awarded to JMAR Construction for a total amount of $10,425.00.
• The key points of the contract include the removal of existing windows, installation of new windows, and completion of any necessary work to give an air-tight seal.
• The contract includes the replacement of eight windows, with six being double slider style and two being solid non-slider style.
• The contractor is responsible for all measurements and is required to meet with the Fairgrounds Staff to view the project.
• The contract includes a pre-bid conference, which was held on November 3, 2009, at the Fairgrounds Pavilion.