The contract is for the resurfacing of Portage Lakes Dr. (CH 75) in Summit County, Ohio. The project includes pavement planing and asphalt concrete overlay, as well as the installation of new storm sewer catch basins, curbing, paved shoulders, and guardrail. The engineer's estimate for the project is $317,148.87, and the completion date is July 31, 2019. The contract was awarded to multiple vendors, including karvo Companies Inc., Barbicas Construction Co Inc, and Chagrin Valley Paving, Inc.
• The project involves resurfacing a 0.31-mile stretch of Portage Lakes Dr.
• The contract includes the installation of new storm sewer catch basins, curbing, paved shoulders, and guardrail.
• The engineer's estimate for the project is $317,148.87.
• The completion date for the project is July 31, 2019.
• The contract was awarded to multiple vendors, including karvo Companies Inc., Barbicas Construction Co Inc, and Chagrin Valley Paving, Inc.