The contract is for the construction of a refueling station at the Montevue Campus. The work includes the installation of sediment control measures, stormwater management systems, electrical service, and fuel pumps. The contract also includes the demolition and removal of existing fuel tanks and associated components. The preliminary bid tabulation lists two vendors, Petroleum Management Inc. and WM Schlosser Co. Inc., with prices of $4,323,146.00 and $4,633,000.00, respectively.
• The contract is for a refueling station at the Montevue Campus.
• The work includes installation of sediment control measures, stormwater management systems, electrical service, and fuel pumps.
• The contract also includes demolition and removal of existing fuel tanks and associated components.
• Two vendors are listed in the preliminary bid tabulation, with prices ranging from $4,323,146.00 to $4,633,000.00.