This contract is for improvements to the trail system at Willow Waterhole Detention Basin in Precinct 1 of Harris County. The project includes the construction of 2.94 miles of concrete trail and 0.6 miles of earth trail. The contract was awarded to MB Western Industrial Contracting Co. for an amount of $2,368,844.15. The project is expected to improve existing pedestrian facilities within the detention basin and align with the county's goals of public health, environment, and governance. Some key features of the contract include:
• The contract is for a single vendor, MB Western Industrial Contracting Co.
• The project is expected to be completed within 365 days.
• The contract amount is $2,368,844.15.
• The funding source for the project is the Mobility Fund.
• The project is not an emergency, disaster, or COVID-19 related item.