The Amsden Wildlife Habitat Management Area Fencing Project involves the tear out and replacement of eight foot tall woven wire elk fences, inlets, and elk jumps at the Amsden WHMA. The project requires the contractor to provide all labor, materials, and equipment to perform the work. The contract was awarded to three vendors: Black Fern Fencing, Boot Hill Construction, and Fireproof Foundations, with total bid amounts of $403,920.00, $495,000.00, and $790,000.00 respectively. The project has a mandatory pre-bid meeting and requires the contractor to sign a bid bond.
• The project is located at the Amsden WHMA, approximately four miles west of Dayton, WY.
• The contractor must provide all labor, materials, and equipment to perform the work.
• The project requires a mandatory pre-bid meeting.
• The contractor must sign a bid bond.
• The contract was awarded to three vendors with total bid amounts ranging from $403,920.00 to $790,000.00.