This contract awards the City of Mobile a $447,647 construction project to build Section A of the Three Mile Creek Biking & Walking Trail. The work includes constructing concrete sidewalks, pedestrian bridges, parking areas, and lighting fixtures, all under a Community Development Block Grant (CDBG) funded framework that requires compliance with federal civil‑rights, prevailing‑wage, and HUD regulations. The project was procured through an open competitive bidding process, with a mandatory pre‑bid conference on December 6, 2016, and a sealed bid deadline of December 14, 2016. The successful bidder, James Adams & Son, must provide bid and performance bonds, appropriate insurance, and hold an Alabama contractor license (MU or HS classification).
• Multi‑use trail segment with concrete sidewalks, bridges, parking, and lighting.
• Funded by HUD’s CDBG program, requiring strict federal compliance and prevailing‑wage payment.
• Open competition with a 5 % bid‑bond ceiling ($50 k) and full performance‑bond requirement.