The contract is for the installation of a new carbon adsorption system at the Elk Grove Landfill, including demolition and removal of the existing enclosed flare system. The project has an estimated construction cost of $160,000. The contract was awarded to Bob Sonn Excavating, DBA BSE General Electric, with a bid of $84,937.10.
• The project includes installation of a new carbon adsorption system
• Demolition and removal of the existing enclosed flare system
• Estimated construction cost is $160,000
• The contract was awarded to Bob Sonn Excavating, DBA BSE General Electric