The Outer Loop Road Slope Improvement contract covers the excavation, drainage, fencing, and traffic‑control work required to stabilize three slope sections along the Outer Loop Road in Prescott, Arizona. The scope includes roughly 11,610 cubic yards of earthmoving, installation of new barbed‑wire fencing, construction of top‑of‑slope ditches, and placement of temporary concrete barriers and impact attenuators to maintain traffic flow. The project is a short‑duration, fixed‑price, unit‑price contract with a 16‑day construction window once the Notice to Proceed is issued.
• Primary work: road‑side earthwork, ditch construction, fence removal/installation, and temporary traffic‑control devices.
• Contractor: Asphalt Paving & Supply, Inc., required to provide a 10 % bid bond and 100 % performance and payment bonds.
• Schedule: Bids due April 24 2025; award announced May 21 2025; NTP June 2 2025; work completed by mid‑June 2025.