The City of Independence, Missouri, awarded a contract for filter media removal to RK Hydro-Vac, Inc. The project involves the removal of sand media from Filters No. 5 and No. 6 at the Courtney Bend Water Plant. Filter No. 6 shall be completed within 20 calendar days after Notice to Proceed is given, and Filter 5 will be scheduled at a later date, some time after February, 2013 if completed. The key aspects of this contract include the removal of filter media, the completion of Filter No. 6 within a specific timeframe, and the potential for Filter 5 to not be completed as part of this contract. Some key points to consider are:
• The project location is at the Courtney Bend Water Plant, 3008 N. Cement City Road, Sugar Creek, MO 64053.
• The bid submission date was December 18, 2012.
• The City of Independence, Missouri, is the agency that awarded the contract.
• RK Hydro-Vac, Inc, is the vendor that was awarded the contract.
• The contract duration is at least 20 calendar days for Filter No. 6.
This contract is relevant to companies that specialize in filter media removal, water treatment, and environmental services.