The Ridge Manor Water Reclamation Facility Expansion & Emergency Operations Structure project involves the construction of a new water reclamation facility and an emergency operations structure. The new facility will have a capacity of 2.0 MGD, with a bid alternate of an additional 1.0 MGD. The project also includes the construction of new rapid infiltration basins and the installation of equipment, yard piping, sitework, electrical and instrumentation, and generators. The emergency operations structure will be a 2,500 square foot site-built concrete split face block structure with general office space, a large conference room, breakroom, restrooms, and general mechanical/SCADA rooms. The structure will serve as the office for the new water reclamation facility and will also be used in times of declared state of emergencies.
• The project requires a general contractor with experience in construction of concrete tankage and installation of equipment, yard piping, sitework, electrical and instrumentation, new buildings, and generators.
• The project includes the construction of new rapid infiltration basins and the installation of equipment, yard piping, sitework, electrical and instrumentation, and generators.
• The emergency operations structure will be a 2,500 square foot site-built concrete split face block structure.
• The project requires compliance with all applicable laws and regulations, including those related to excavation and utility locates.
• The project requires the submission of a bid bond, certified check, or cashier's check in the amount of not less than 5% of the total base bid amount.
• The project requires the submission of a proposal that includes all required documents and information, including references, licenses, and certifications.