This RPQ calls for the demolition, site preparation, concrete and asphalt work, installation of two new 8′ × 20′ steel EMS containers, a new single‑wide modular trailer, a canvas canopy, GearGrid lockers, and a Genetec card‑reader access system at two Miami‑Dade Fire Rescue stations (18T and 41T). The contractor must provide all design submittals, obtain permits, supply portable toilets, and perform all electrical, plumbing, HVAC, and low‑voltage work while complying with fire‑rescue operational constraints. The contract is capped at $800 k, with a 240‑day construction schedule and liquidated damages for delays.
• Demolition of existing asphalt, canopy, trees, and other obstructions at both sites.
• Installation of a 6‑in. monolithic concrete slab, new asphalt paving, and site‑grade improvements.
• Supply and install two high‑cube steel EMS containers, a single‑wide modular trailer, canvas canopy, GearGrid lockers, and a Genetec security access system.
• Full electrical, plumbing, HVAC, low‑voltage, and site‑utility connections, plus required permits, safety measures, and a three‑year labor warranty.