The project involves a comprehensive refurbishment of the Beaver Ruin Diversion Pump Station’s mechanical, civil, and electrical systems to restore reliable water‑treatment operations. The scope includes replacing grinder units, slide‑gate actuators, concrete wet‑well structures, and associated electrical conduit and motor control equipment, all within a 450‑day construction window.
• Replace three grinder units with new rail systems, channel modifications, and control panels.
• Replace and install actuators for three influent slide gates, three effluent slide gates, two influent wet‑well slide gates, and one wet‑well crossover slide gate.
• Raise concrete wet‑well baffle wall and platform elevations; relocate and reinstall the existing flushing system.
• Install new electrical conduit, motor control center (MCC) configuration, and related wiring.
• All bidders must purchase the complete set of drawings/specifications ($250 fee) and may attend an optional pre‑bid conference on 1 Sept 2026 at the site.
You found this one too late. Don't find the next one too late.
Bid Banana searches open government bids across all 50 states, updated daily. Save a search once and we email you your new matches, daily or weekly, while there is still time to win them.