The Village of Gurnee is seeking a qualified contractor to replace and upgrade water‑main infrastructure in the Estes region. The scope includes installing new 6‑in. and 8‑in. PVC water mains, fire hydrants, gate valves, water‑service connections, culvert replacement, storm‑sewer water‑main quality pipe, and extensive site work such as excavation, topsoil placement, and asphalt paving. A $1 million drainage pre‑qualification from IDOT is required, along with prevailing‑wage compliance and a licensed plumber for all service connections.
• Install approximately 6,720 LF of 6‑in. PVC C900 water main and 2,770 LF of 8‑in. PVC C900 water main (open‑cut and HDD).
• Provide fire‑hydrant installations, gate valves, 118 water‑service connections, and related utility relocations (culverts, storm‑sewer pipes).
• Perform extensive site preparation: earthwork, topsoil furnishing (14,000 SY), asphalt paving (≈2,490 tons hot‑mix) and a new leveling‑binder item (1,250 tons).
• Must submit IDOT drainage pre‑qualification, BC‑733 Certificate of Eligibility, BC‑57 Affidavit of Availability, and a proposal guarantee; all bids sealed and opened on February 9, 2026.