The Institute for Basic Research intends to procure replacement of the burner on a steam boiler. The project involves removing the existing dual-fuel burner and installing a new customer-provided Weishaupt dual fuel burner with remote/free standing burner control panels. The contractor must provide all labor and materials necessary to complete the work in a professional manner according to the scope of work and architectural drawings. The project must be completed within 30 days of award, and prevailing wages must be paid. A mandatory site visit is scheduled for October 14, 2025, at 10:00 AM.
• The contractor must remove the existing dual fuel burner and install a new customer-provided Weishaupt dual fuel burner with remote/free standing burner control panels.
• The contractor must furnish and install new customer-provided Siemens gas trains, steam pressure transducers, and temperature probe for low fire hold.
• The contractor must furnish and install new customer-provided Hays Cleveland draft controls, actuators, smoke opacity monitors, thermocouple meter.
• The contractor must conduct comprehensive start-up, functional testing, and performance verification of the installed burner system.
• The contractor must provide certificates of Liability Insurance and Worker’s Compensation Insurance.
• The contractor must comply with all applicable laws and regulations, including prevailing wage requirements.