This contract calls for the replacement of eight pool heaters across multiple high schools in the Chaffey Joint Union High School District. The work is limited to demolition of existing equipment, site preparation, disposal, installation of new Lochinvar and Raypak heaters, and commissioning. Bidders must hold California C‑61 and D‑35 licenses, attend a mandatory pre‑bid conference, and complete the project within 64 days to avoid $1,000 per day liquidated damages.
• Replace eight pool heaters (Lochinvar/Raypak) at several district high schools
• Requires C‑61 and D‑35 contractor licenses; prevailing‑wage rules apply
• Mandatory pre‑bid conference on March 5, 2026; bid due March 17, 2026 (2 pm)
• Project budget estimate $1.2 million; 64‑day construction window with $1,000/day liquidated damages