This municipal project in Habersham County, GA requires a contractor to mill, patch, level, resurface, and stripe 12.35 mi of county‑ and town‑road pavement. The work includes installing Open‑Graded Interlayer (OGI), applying 9.5 mm and 12.5 mm Super‑pave surface courses, tack coating, and full traffic‑control striping, all in compliance with GDOT specifications. The contract is fixed‑price, with performance and payment bonds, and carries a liquidated‑damage penalty of $1,500 per day for late completion.
• Scope: 11.93 mi of county roads + 0.42 mi of town roads (≈ 12.35 mi total) – milling, resurfacing, OGI, Super‑pave layers, tack coat, and striping.
• Schedule: Pre‑bid meeting mandatory May 20, 2026; bid due May 29, 2026 2 PM; award expected June 16, 2026; project completion Oct 9, 2026 (≈ 16 weeks).
• Requirements: GDOT‑approved mix designs, full insurance (≥ $2 M GL), 5 % bid bond, performance & payment bonds (100 % of contract), E‑Verify affidavits, and compliance with traffic‑control and erosion‑control standards.