The contract is for the demolition of the Unit #4 chimney and all structural attachments at the Silver Lake Plant. The contractor is responsible for determining the best method of removal of all associated debris at their expense. The bid proposal, including a copy of the bid bond and all supporting documents, must be submitted electronically to the website. The contract has a mandatory pre-bid meeting, and vendor attendance is required. The key aspects of this contract include the demolition of the chimney, removal of debris, and submission of bid proposals.
• The contract requires the contractor to provide all labor, rigging, tools, equipment, work platforms, and materials to fully remove the Unit #4 chimney and all structural attachments.
• The contractor is responsible for determining the best method of removal of all associated debris at their expense.
• The bid proposal, including a copy of the bid bond and all supporting documents, must be submitted electronically to the website.
• The contract has a mandatory pre-bid meeting, and vendor attendance is required.
• The contract includes various documents, such as instructions to bidders, general terms and conditions, chimney demo specifications, and exhibit documents.