This addendum updates the demolition scope for the small gym at Gabrielino High School. It clarifies assumed as‑built conditions, adds a five‑day extension to the demolition schedule, and outlines the requirement for a 10‑day AQMD asbestos‑abatement notification after award. The contractor will be responsible for full demolition of the concrete tilt‑up wall, its footing, and all associated structural elements, and must be prepared to handle any asbestos‑related work in compliance with California regulations.
• Full‑height tilt‑up concrete wall and 3 ft × 3 ft footing (75 ft long) must be demolished.
• Exterior wall heights of 26 ft (main) and 13 ft (remaining) are assumed for bid calculations.
• Schedule is extended by five calendar days at the start of the project.
• After award, a Letter of Intent triggers a mandatory 10‑day AQMD notification for asbestos abatement.
• No on‑site work may begin until the contract is fully executed.
Attached files
Similar opportunities
Matched by Bid Banana AI™
Bid Banana · 1.6M+ bids and awards 🍌
You found this one. Bid Banana has 1.6M+ bids and awards.
You found this bid by looking. Bid Banana searches open government bids across all 50 states, updated daily, so you stop hunting: save a search once and we email you your new matches, daily or weekly.