The City of Bellevue is seeking bids for the construction of 124th Avenue NE - NE 12th Street to NE Spring Boulevard. The project includes removal of structures and obstructions, cement concrete curb and gutter, asphalt concrete pavement, and other improvements. The engineer's estimate for the project is $8,221,853.93. The contract was bid on by five vendors, with prices ranging from $8,701,145.81 to $11,663,166.69.
• The project includes multiple components, such as removal of structures and obstructions, cement concrete curb and gutter, and asphalt concrete pavement.
• The engineer's estimate for the project is $8,221,853.93.
• Five vendors submitted bids for the project, with prices ranging from $8,701,145.81 to $11,663,166.69.
• The contract is being managed by the City of Bellevue's Finance Department, Contracting Services.
• The project manager for the contract is Marina Arakelyan.