The contract is for the rehabilitation of the Cougar Mountain 1 Pump Station, which includes structural improvements, pump replacement, new generator installation, electrical improvements, yard piping modifications, site improvements, frontage improvements, and installation of new instrumentation and controls system components. The contract was awarded to multiple vendors, with the lowest bid being $2,696,073.75. The project includes various items such as mobilization/demobilization, trench/excavation protection, construction surveying and as-builting, demolition, site water main piping, valves, and accessories, reservoir overflow and storm drain improvements, site work and restoration, hot mix asphalt, crushed rock, pumps and motors, and electrical work.
• The project requires the rehabilitation of the pump station, including structural improvements and pump replacement.
• The project includes the installation of a new generator and electrical improvements.
• The project requires yard piping modifications, site improvements, and frontage improvements.
• The project includes the installation of new instrumentation and controls system components.
• The contract was awarded to multiple vendors, with the lowest bid being $2,696,073.75.