The City of Palm Bay, Florida, has awarded a contract for the construction of nutrient removal facilities at the North Regional Water Reclamation Facility. The contract includes the demolition of an existing water tank and the construction of a new process tank, as well as associated piping and appurtenances. The facility must remain operational during construction, and any required bypass or shutdown must be approved in writing by the owner and engineer. The contract was awarded to TLC Diversified, Inc. for an amount of $3,367,000.00.
• The contract includes the construction of a two-compartment biological treatment structure and equipment related to the Modified Ludzack-Ettinger biological reactor wastewater treatment process.
• The contract also includes the installation of an alum bulk storage and chemical feed system, as well as instrumentation, controls, and integration into the existing plant SCADA control system.
• The contractor is responsible for all associated site improvements, including paving, grading, sidewalk restoration, seeding and mulching, fencing, and other improvements as shown on the contract drawings.
• The contractor is also responsible for any necessary dewatering, temporary controls, erosion, and sediment controls.