The Neal Road Recycling and Waste Facility 2017 GCCS Modification Plan is a project that involves the installation of landfill gas HDPE piping, horizontal gas collection wells, landfill gas well head connection manifolds, and condensate drainage traps. The project is located in Paradise, Butte County, California, and was advertised on March 15, 2017. The bid opening date was March 28, 2017. The project has a total of 11 items, including mobilization, surveying, trench excavation, and piping installation. The engineer's estimate for the project is $222,930.00.
• The project involves the installation of landfill gas HDPE piping and horizontal gas collection wells.
• The project is located in Paradise, Butte County, California.
• The bid opening date was March 28, 2017.
• The engineer's estimate for the project is $222,930.00.
• The project has a total of 11 items, including mobilization, surveying, trench excavation, and piping installation.