The contract is for the Flint Creek State Water Project Main Canal Improvements, which involves rehabilitation improvements to two sections of the Flint Creek Main Canal to address seepage, hydraulic capacity, conveyance, and improve maintenance access routes. The project includes installation of 1,200 feet of canal liner and rehabilitating 3,850 feet of the canal. The contract was awarded to Glacier 3D, LLC.
• The project consists of two main components: Schedule 1 and Additive Alternate 1.
• Schedule 1 includes installation of 1,200 feet of canal liner.
• Additive Alternate 1 includes rehabilitating 3,850 feet of the canal.
• The contract was solicited through an Invitation for Bid (IFB) process.
• The IFB was issued on June 4, 2025, and bids were due on July 1, 2025.
• The contract was awarded on July 15, 2025.