The City of Boise is seeking to replace the main 34.5 kV pad-mounted transformer at the Boise Airport with a new Idaho Power transformer. The project includes coordination with Idaho Power to provide the new transformer, modification of the existing medium voltage infrastructure, and civil site work. The contract was awarded to Bodec for a total bid of $492,862.00. The project involves electrical upgrade work, including the replacement of the transformer, underground conduit, medium voltage feeders, and new switchgear sections. The City of Boise reserves the right to reject any and all bids, and the contract is subject to the terms and conditions outlined in the solicitation document.
• The project involves electrical upgrade work at the Boise Airport.
• The contract was awarded to Bodec for a total bid of $492,862.00.
• The project includes coordination with Idaho Power to provide the new transformer.