The Municipality of Skagway contracted Hamilton Construction to extend the Skagway Small‑Boat Harbor launch ramp. The project adds a 30‑ft timber float extension, two precast concrete ramp lanes, new steel‑pipe pile foundations, excavation, armor‑rock slope protection, and related site improvements. It is a unit‑price contract with a total award ceiling of $724,750.75 and a schedule that runs from mid‑October 2022 to mid‑May 2023.
• Scope includes timber float extension, concrete ramp planks, steel‑pipe pile installation, and armor‑rock placement.
• Required compliance with U.S. Army Corps Nationwide Permit 36 and a Letter of Permission (expires 2027).
• Contractor must furnish a 5 % bid bond, 100 % performance and payment bonds, and maintain specific insurance and prevailing‑wage obligations.