This municipal bid tabulation details the construction, removal, and related civil works for the Brooks Street Fire Department driveway in Galesburg, IL. The scope includes installation of geofabric, two thicknesses of aggregate base course, two concrete pavement thicknesses, a concrete sidewalk, removal of existing pavement and sidewalk, and installation/removal of a single inlet. Ten line‑items are quantified, with total quantities ranging from 1 to 135 units. Seven contractors submitted bids, providing unit prices and total costs; the lowest total bid recorded is approximately $33,437, while the highest is about $53,888. No award decision is included, so the contract remains in the pre‑award phase. The project is funded by the City of Galesburg’s purchasing department and reflects a typical competitive municipal construction procurement.
• Scope: geotechnical fabric, aggregate base, concrete driveway and sidewalk, demolition, and inlet work.
• Quantities: 77 SY geo‑fabric, 63 SY agg‑2”, 77 SY agg‑8”, 59 SY PCC‑6”, 77 SY PCC‑10”, 40 SF sidewalk, 135 SY driveway removal, 40 SF sidewalk removal, 1 EA inlet install, 1 EA inlet removal.
• Competition: seven bidders submitted unit‑price proposals; award still pending.