Outagamie County’s Northwest Landfill Phase 1 project involves the construction of a 20.4‑acre composite‑lined municipal solid‑waste landfill, including a clay liner, geomembrane, geocomposite drainage layer, leachate collection and pump system, access roads, and site restoration. The contract was awarded to Relyco via a sealed‑bid competitive process, with a total bid price of approximately $6.03 million. The scope covers extensive earthwork, liner installation, leachate handling infrastructure, electrical and gas systems, asphalt paving, and final site reclamation, all to be completed by 1 Sept 2025. Key contract provisions include a 5 % bid bond, performance and payment bonds equal to the contract sum, mandatory insurance (minimum $1 M CGL, $5 M umbrella), liquidated damages of $10 k per day for late completion, and a requirement to store geosynthetics on‑site in 2024.
• Composite landfill construction (clay + geomembrane) with leachate collection and pump system.
• Full‑scope civil, structural, mechanical, and electrical works including roadways, power distribution, and site restoration.
• Fixed‑price contract with strict schedule (substantial completion by 1 Sept 2025) and liquidated‑damage penalties.