The contract is for the establishment of a new mid-block crossing on W Lk Sammamish Pkwy SE, near the Little Store. The project work includes removing and replacing asphalt concrete pavement shoulder, installing cement concrete landings, truncated domes, RRFB system, pavement markings, signing, property restoration, and other miscellaneous work. The contract was awarded to multiple vendors, with the total bid prices ranging from $90,038.81 to $126,320.00. The engineer's estimate for the project is $105,000.
• The project involves mid-block crossing construction
• The project includes asphalt concrete pavement shoulder removal and replacement
• The project includes installation of cement concrete landings, truncated domes, and RRFB system
• The project includes pavement markings, signing, and property restoration
• The contract was awarded to multiple vendors
• The total bid prices range from $90,038.81 to $126,320.00