The State of Utah, Division of Facilities Construction and Management (DFCM), is requesting bids for the construction of the Cal Rampton Courtyard Concrete Replacement project. The project involves removing and replacing various areas of concrete around the courtyard and complex. The construction cost estimate is $278,000.00. The bid documents are available on the Utah Public Procurement Place (U3P) website and the DFCM website. A mandatory pre-bid meeting and site visit were held on August 13, 2024. The contract was awarded to three vendors: Wasatch West Contracting, LLC, Sunset Mountain Machinery LC, and Gladwell Construction LLC.
• The project location is 4501 S 2700 W, Taylorsville, Utah 84129.
• The project completion date is 05/26/2025.
• The bid submission date was 08/29/2024.
• The construction cost estimate is $278,000.00.
• The contract was awarded to three vendors.
• A mandatory pre-bid meeting and site visit were held on August 13, 2024.