This contract calls for the design‑build construction of the SR 530 Slide Memorial in Snohomish County, Washington. The work includes complete site preparation, grading, utility installations, concrete foundations, structural steel and rebar, landscaping, installation of site‑furnishings (benches, bollards, bike racks, interpretive exhibits), and all associated permitting, inspections, and project administration. The award is a lump‑sum contract valued at just under $4 million, awarded to Konnerup Construction Inc, a Washington‑licensed general contractor. The county’s purchasing division managed the procurement through an open competition, with bids due August 30 2022 and the award issued September 22 2022.
• Scope covers earthwork, concrete, steel, rebar, landscaping, and park equipment installation.
• Contractor must provide performance, payment, and warranty bonds (5 % of the total bid) and comply with Washington wage‑payment statutes and apprenticeship utilization goals.
• No set‑aside requirements or mandatory DBE/MBE participation were imposed.