This contract is for the construction of ARPA 71st St from 38th Ave N to 54th Ave N (PID 004539A) STEP 2. The project involves various road construction and drainage activities, including surveying, excavation, pipe installation, and traffic control. The contract was awarded to Kamminga & Roodvoets, Inc. for a total amount of $13,401,806.15. The project is expected to last for 720 days.
Key points of this contract include:
• Construction of ARPA 71st St from 38th Ave N to 54th Ave N (PID 004539A) STEP 2
• Various road construction and drainage activities
• Surveying, excavation, pipe installation, and traffic control
• Contract awarded to Kamminga & Roodvoets, Inc.
• Total contract amount: $13,401,806.15
• Project duration: 720 days