The City of Prescott contracted a general contractor to construct a clean‑room within Fire Station 71. The scope includes framing and wall construction, full plumbing, HVAC installation (new rooftop unit), and complete electrical work, all delivered as lump‑sum items. The project is funded by municipal dollars, requires a 10 % bid guarantee, full performance and payment bonds, and adherence to city‑standard specifications, with a 24‑month warranty and standard insurance requirements.
• Scope: Clean‑room build‐out (walls, HVAC, plumbing, electrical) inside an existing fire station.
• Schedule: Notice to Proceed week of Oct 27 2025; 180‑day construction period (≈ early May 2026).
• Award: Ridgeline Builders, LLC won with a $110,875.74 lump‑sum bid; contract is firm‑fixed‑price.